Sunday, December 16, 2007
Rocky Branch on BOC Agenda Again
The upgrade to the Rocky Branch sewage treatment plant, which will result in the discharge of up to 1 million gallons per day of treated wastewater into Barber Creek, is back on the agenda of the Board of Commissioners for its meeting on Tuesday, December 18.
The BOC will be updated by Precision Planning’s Jimmy Parker and Oconee Utility Department Director John Hatcher on "Wastewater Planning and RFP Update."
The deadline for submission of proposals for the upgrade of the Rocky Branch plant is 5 p.m. the day before the BOC meeting.
In addition, the BOC will hear from Parker and Hatcher about "water resources" at the Tuesday meeting.
I’ll also ask for the third time that the Board pass a resolution drafted by the Georgia Water Coalition. The resolution asks the Georgia General Assembly to fund water resource study and monitoring and to oppose interbasin transfers of water. The Board has refused to take any action on the resolution despite two earlier requests by me that it do so.
After promising to follow a different course of action, the County essentially reissued the Request for Proposal it had issued in June for engineering and design work on the Rocky Branch sewage plant. That request had produced three bids, and the Utility Department wanted to give the project to Jordan Jones and Goulding.
JJ&G was not the low bidder and had been involved in initial planning work for the plant. Precision Planning, which had partnered with JJ&G on County projects, also participated in the review that led to selection of the JJ&G bid.
JJ&G, on a tip from the County, proposed that the County abandon its commitment to membrane filtration for the plant and use a more primitive treatment method. That method cannot meet the standards that membrane filtration is capable of meeting.
The BOC refused to go along with the recommendation of the Utility Department after I pointed out the nature of the bidding and review. You can read details of that meeting in my posting of 9/10/2007.
Alan Theriault, administrative officer for the County, sent me an e-mail message on September 7, three days after the Board of Commissioners (BOC) voted to upgrade the Rocky Branch plant, saying he expected the initial step in the rebidding process to be a "Request for Qualifications" advertisement "to identify design firms or teams that have specific experience with membrane filtration wastewater systems and that would be interested in this project."
Although I have asked Theriault twice since that September message to keep me updated on discussions about Rocky Branch, he did not inform me about the new bidding for the plant upgrade.
Advertisements for the project appeared in The Oconee Enterprise on November 21 and 29 and again on December 6 and 13. The advertisements are nearly identical to those used for the earlier bid.
As with the earlier bid, interested parties were required to participate in a pre-submittal conference. That conference, according to the advertisements, was held on December 4, making the last two advertisements in the Enterprise meaningless, at least in terms of soliciting proposals.
My efforts to get the BOC to pass the Georgia Water Coalition resolution have produced nothing. The issue is the interbasin transfer prohibition, Chairman Melvin Davis has confirmed.
The County has a permit for an interbasin transfer for the Hard Labor Creek reservoir project. Water will be pumped out of the Oconee River basin and discharged, at least partially, into the Ocmulgee River basin. In addition, Oconee County sold water to Walton County for many years, and that water came out of the Oconee River basin. Walton County straddles the Oconee and Ocmulgee basins.
If the County would discuss the Water Coalition resolution, its stand on future interbasin transfers might become known. Even if the County does not pass that part of the resolution dealing with interbasin transfers, it could pass the other part, dealing with funding for the study of water issues.
My blog posting of 11/23/2007 explains the resolution.
By the way, if you missed the lead story in today’s Athens Banner-Herald about a broken promise to citizens in Clarke and Olgethorpe Counties about a landfill, you might want to take a look. It tells how important it is for citizens to watch what government officials do, and how hard it is to control those actions.
If you can attend the meeting tomorrow night, please do so. It always helps to have a crowd.
Friday, November 23, 2007
Georgia Water Coalition Petition
The Board of Directors of Friends of Barber Creek has asked the Oconee County Board of Commissioners to support a resolution drafted by the Georgia Water Coalition to respond to the current drought crisis.
Here is the text of a letter I sent to Mr. Melvin Davis, chairman of the Oconee County BOC, asking for BOC support.
November 23, 2007
Mr. Melvin Davis, Chairman
Oconee County Board of Commissioners
Oconee County Courthouse
23 N. Main Street
Watkinsville, GA 30677
Dear Mr. Davis:
The Georgia Water Coalition, a group of individuals and organizations working to ensure that the waters of the state continue to belong to the people of the state, has drafted a resolution regarding water policy in Georgia. Friends of Barber Creek, one of the 149 Georgia Water Coalition partners, is asking the Board of Commissioners of Oconee County to pass this resolution on behalf of the citizens of Oconee County. A copy of the resolution is below.
The purpose of the resolution is to guarantee fair apportionment of Georgia's waters to all portions of the state. This resolution asks the General Assembly to provide full funding for water planning on a regional and state level. It also asks for legislation prohibiting future transfers of water across the 14 river basins in the state.
The ongoing drought has made citizens of Oconee County and of the state aware of the precious nature of our water resources. The response to the drought indicates that the state currently lacks the information it needs to ensure that this resource will be managed sustainably in the future to balance the needs of natural systems, downstream economies, and other uses such as recreation, power generation and industry.
Because much of the population growth to date has occurred in the northern part of the state, where numerous rivers have their headwaters, water historically has been transferred from one river basin to another to meet increasing human demands. These transfers unfairly rob the donor basin of water that should flow downstream to support other economies and uses. More and larger transfers may occur in the future if this pattern is not halted by the legislature.
Through its partners, the Georgia Water Coalition is presenting this resolution to governing authorities across the state. The following entities already have passed the resolution: Putnam County, LaGrange, Liberty County, Chatham County, Rome, Floyd County, City of Tybee, Brantley County, City of Metter, Evans County, Hart County, City of Lavonia, City of Hartwell, Bryan County, Troup County, Ware County and the Satilla Regional Water and Sewer Authority.
The Board of Directors of Friends of Barber Creek urges the Oconee County Board of Commissioners to pass this resolution expeditiously so Oconee County can offer its support for the Georgia Water Coalition’s efforts to ensure that water is managed fairly for all Georgians, with the interest of all citizens, businesses and farms in mind.
I will attend the Board of Commissioners Agenda Meeting on November 27 to ask you either to pass this resolution or schedule it for discussion at your December 4, 2007 meeting.
Sincerely,
Lee B. Becker
President, on behalf of the Board of Directors of Friends of Barber Creek
Lee B. Becker, President (1050 Scott Terrace)
Tim Price, Vice President (1240 Hollow Creek Lane)
Mailing Address for Friends of Barber Creek:
1050 Scott Terrace
Athens, GA 30606 (Oconee County)
Tel. 706 548-1525
RESOLUTION
WHEREAS, there is increased pressure on the surface and ground water resources within the State of Georgia, but a lack of information as to the natural quantities of water in its rivers and aquifers, and
WHEREAS, the Oconee County Board of Commissioners believes that the surface and ground waters of the state should continue to be managed in the public interest and in a sustainable manner to protect natural systems and meet human and economic needs, and
WHEREAS, protection and restoration of water resources requires regional water planning, based on assessments of watersheds, river basins, and aquifers, that is tied to implementation, including a comprehensive management process, and
WHEREAS, protection of river basins must be strengthened to reflect scientific knowledge and respect natural systems, and
WHEREAS, downstream communities in Georgia rely on certain flow levels in river basins for current and future economic development, recreation, and environmental quality, and
WHEREAS, decisions on new water supplies for growing communities should recognize that efficiency and the wise use of current resources are the best course for taxpayers, and
WHEREAS, transferring water from one basin to another can adversely affect downstream communities and unfairly redistribute economic growth,
NOW THEREFORE, BE IT RESOLVED THAT the Oconee County Board of Commissioners supports and adopts the principles outlined above and urges the General Assembly of Georgia to fully fund comprehensive regional and statewide water planning and monitoring,
AND, BE IT FURTHER RESOLVED THAT the Oconee County Board of Commissioners urges the General Assembly of Georgia to pass a statute that prevents the transfer of water from one basin to another to the detriment of current and future downstream economic growth or to the detriment of the natural health of the stream.
Duly adopted the _____day of __________, 2007.
Wednesday, October 17, 2007
Rare Chance to See Elder Mill, Other Sites
Oconee County residents will get a rare chance on Saturday to tour a part of southern Oconee County that, to date, has been spared from development and that contains a number of important historical sites.
Unfortunately, the area is threatened, and the Board of Commissioners has yet to take any action to protect it.
The Elder family will be directing people to family sites in the County, such as the Elder Mill Covered Bridge on Rose Creek, Elder Mill, and two family cemeteries. Maps for the sites will be available Saturday at the Elder shop, between the courthouse and the Haygood House on Main Street in Watkinsville.
Watkinsville is the site of the Saturday’s Oconee Fall Festival, and the Elder family will hold a reunion at the Watkinsville shop. The public is invited.
Cokey Elder, a senior member of the family, said the mill, located on Rose Creek near the covered bridge, will be open for viewing as part of the tour.
Only the bridge, which carries limited traffic across Rose Creek on Elder Bridge Road just south of SR15, is owned by the County. The surrounding land and the mill are in private hands.
The BOC discussed creating a park that would include the bridge and at least some surrounding property in a closed-door session on September 4. No details of the discussion or of the proposed park have been released to the public.
After returning to regular session from the closed-door discussions on September 4, the BOC voted to continue to pursue a grant from the Georgia Land Conservation Program to help create the park, but the BOC refused to allocate any funds to support the application.
Following that closed-door session, according to the minutes, "On motion by Commissioner (Chuck) Horton and second by Commissioner (Jim) Luke, the Board voted unanimously to continue with the GLCP grant request for the proposed Elder Mill Park as originally submitted, providing no monetary funding obligation from the County, only in-kind funding."
According to the historical marker at the Elder Bridge, it was built in 1897 and carried the Watkinsville-Athens road across Calls Creek, which flows from Watkinsville to the Middle Oconee River north of Watkinsville.
The 99-foot-long bridge was moved to its present location in 1924. The bridge is made entirely of wood, and its planks are held together with wooden pegs.
The grist mill, just downstream from the bridge, was built about 1900 and stopped operating in 1941, according to the marker at the bridge. It contains many of the original inner workings of the mill.
Rose Creek between the bridge and mill flows over large rocks, creating a shoal, and is surrounded by large hardwoods.
Some of the key tracts of land surrounding the bridge and mill are designated by the County as protected in the proposed new land use map. The County largely ignores its current land use map, and it could ignore the new one should it be adopted.
Any development along Elder Bridge Road or Saxon Road would be a threat to the bridge, as it can handle very limited traffic.
Some of the property is certainly attractive for development. A subdivision already has been laid out on SR 15 between Watkinsville and the site.
According to Georgia open meeting laws, the BOC was allowed to go into a secret session if it was "discussing the future acquisition of real estate."
The BOC is still required to prepare "minutes of such a meeting; provided, however, the disclosure of such portions of the minutes as would identify real estate to be acquired may be delayed until such time as the acquisition of the real estate has been completed, terminated, or abandoned or court proceedings with respect thereto initiated."
According to the law, the minutes of the closed session "shall reflect the names of the members present and the names of those voting for closure, and that part of the minutes shall be made available to the public as any other minutes."
If the closed meeting is devoted only in part to discussion of land acquisition, "any portion of the meeting not subject to any such exception, privilege, or confidentiality shall be open to the public, and the minutes of such portions not subject to any such exception shall be taken, recorded, and open to public inspection."
The law states that "Any person knowingly and willfully conducting or participating in a meeting in violation of this chapter shall be guilty of a misdemeanor and upon conviction shall be punished by a fine not to exceed $500.00."
So far, the County has not released the minutes of the closed session, nor has it indicated who joined the BOC in the session.
Monday, October 08, 2007
Water on the Mind
The drought seems finally to have focused almost everyone’s attention on water, or the lack of it.
Consider the following:
*The local papers contain stories nearly every day on the possibility that Oconee and its neighboring counties will run out of water before the end of the year and on the actions local officials have taken in the hopes that the water lasts at least that long.
*Local partners of the state-wide Georgia Water Coalition will hold a meeting from 6 to 8 p.m. on Thursday (October 11) at the Foundry Park Inn Ballroom, 295 E. Dougherty St., in Athens to discuss the state’s first-ever effort to create a water plan for Georgia.
*Oconee County officials are using the drought to justify the County’s decision to join with Walton County to build the $350 million Hard Labor Creek reservoir in Walton County.
The discussion hasn’t focused much attention yet on what local officials could have done to prevent the current crisis or on whether the actions now being taken will prevent such a crisis from occurring again in the future.
An editorial in the October 7 issue of The Atlanta Journal-Constitution, however, has started pointing fingers.
The villain is a mismatch between the water resources of the state and the demands being placed on those resources by development, according to the editorial.
"Georgians can no longer pretend that unchecked growth and the profligate water consumption it fosters can continue indefinitely without exacting a heavy toll," according to the editorial.
The current crisis, the editorial argues, is partly the result of the state’s "unwillingness to recognize the impact of our actions on the state’s limited water resources."
The Hard Labor Creek reservoir project is an interesting case to consider. This reservoir is not designed to address current needs, but rather to provide for future development in the County.
Hard Labor Creek was projected to cost Oconee County $45.6 million in January of 2007, $48.2 million on September 4, when the intergovernmental contract was approved by the Oconee County Board of Commissioners, and $49.8 million on October 4 when the BOC voted to approve a bond contract to cover its portion of the costs.
Only Commissioner Chuck Horton voted against the bond motion, which actually authorized up to $66 million in bond sales, in case the current estimate of $49.8 million is too low. That figure includes $2.9 million Oconee County owes Walton County for money already spent.
The County didn’t even know how much it owed Walton County for past spending when the BOC approved the intergovernmental agreement a month earlier. And the figure, the BOC was told on October 4 by County Attorney Dan Haygood, is still not based on audited expenses, so it could go higher.
Charlie Baugh, president of Citizens for Oconee’s Future and a former Internal Revenue Service auditor, estimates that at 4.4% interest, the County would actually pay $119 million over 30 years for the $66 million, should it borrow that amount.
On September 4, Commissioner Margaret Hale joined Horton in opposing the intergovernmental agreement. Board of Commission Chairman Melvin Davis had to break the tie by joining Commissioners Jim Luke and Don Norris in supporting the agreement.
Whether the final cost is $49.8 million, $66 million, or something even higher, it is supposed to be paid for by growth in the demand for water in the county resulting from future development. Specifically, the demand for water must growth at the rate of at least 8% per year to pay for the reservoir. At present, the County’s population is growing at less than 3% per year.
Most of the water the Oconee County Utility Department sells to its current customers comes from another reservoir, on Bear Creek in Jackson County. Despite the lingering drought, officials from the four counties that run the reservoir–Clarke, Barrow, Jackson and Oconee–did not take dramatic steps to save water until September 13.
On that date, the Upper Oconee Basin Water Operations Committee voted to issue a total ban on outdoor watering effective four days later.
The Committee was just a step ahead of the state. Dr. Carol A. Couch, director of the Georgia Environmental Protection Division, banned outdoor residential water use on September 28 for the four counties and most of the rest of the northern part of the state.
According to former BOC Chairman Wendell Dawson, who says he obtained invoices from the Oconee County Utility Department, Oconee County even sold Walton County 11.3 million gallons of water for a 34-day billing period ending September 27, 2007. According to Dawson, Oconee County sold 87.1 million gallons of water to Walton County in the last six months, when the drought was firmly in place.
So why were Oconee and other officials so slow to take action as the drought progressed?
Selling water is how the counties get the money to build and operate reservoirs and water treatment plants.
For reasons that probably only The Oconee Enterprise editors understand, the paper has given former Oconee County Utility Department head Gary Dodd space for a column in the paper now that he is retired. In addition to using the column to attack critics of the department he headed until this summer, he also is using the column to brag about his accomplishments.
In his October 4, 2007, column, he bragged about the following: "(T)he Utility Department has operated in the black , without a price increase on consumption for the past 8 eights." Not coincidentally, Dodd was Utility Department director during those years.
It is difficult to balance the budget if people stop using water, either because of a ban on watering or because of an imposition of conservation pricing, which pushes down demand by charging a higher rate at higher levels of water consumption. Oconee County does not use conservation pricing.
The impact of the present ban on outdoor watering on water sales and on Oconee County’s ability to pay its expenses through water sales has not been a topic for open discussion just yet. Jackson County, even before the current ban, however, ran into problems making its payments on its indebtedness because of inadequate revenue, according to reporting in the Athens Banner-Herald late this summer.
Counties have few options to make up for lost sales. They can increase water rates, or they can shift the burden onto property owners through higher property taxes.
To pay off current indebtedness and then to finance construction of the Hard Labor Creek reservoir, Oconee County projects it will need for water sales to increase the 8% each year. That includes 2007. Given the current water ban, growth of any sort is unlikely in 2007.
Which helps to explain why the County was so slow in going to the total ban.
Anyone who might have doubted that the decision to move forward with the Hard Labor Creek reservoir was based on a desire to stimulate development only needed to attend the September 4 BOC Meeting.
Amrey Harden, president of Oconee State Bank, Chuck Williams, president of North Georgia Bank, and Charles Grimes, president of the Oconee County Chamber of Commerce, each took their turn to urge the Commissioners to go forward with the project to promote development.
The message likely was directed at Horton and Hale, who still voted against the project. They probably can expect some candidates who got the point to run against them in next Spring’s Republican primary.
The BOC makes lots of routine decision that also have impact on water sales. On August 7 the Board voted (with Horton and Luke in the minority) to approve a rezone request for a development including 196 houses on Old Barnett Shoals road in the far eastern part of the County.
Included was the agreement to extend a water line across the Oconee River to the development. The availability of water will open this area up for additional rezone requests.
The BOC, the current water ban shows, was offering to sell water it doesn’t always have.
The same can be said for efforts of Oconee and Clarke counties to lure a big manufacturer to the Orkin Tract on U.S. 78 and S.R. 316. Included in offers have been the agreement to provide both water and sewage services.
The Georgia legislature mandated the creation of a statewide Water Management Plan back in 2004.
The Georgia Water Coalition, an alliance of over 110 organizations committed to ensuring that water is managed fairly for all Georgians and protected for future generations, has been in existence since 2002.
The Coalition has asked the state to set safe levels of withdrawal from the state’s streams to guarantee their biological, chemical, and physical integrity. The goal is to leave the streams with the water necessary to keep the ecosystems functioning properly. The Coalition wants to require local governments to evaluate and implement conservation measures before increased water withdrawals are allowed.
In sum, the Coalition wants to focus on conservation and maintenance of stream flow, rather than simply allowing the government that gets the water into a reservoir first to have what it wants.
Friends of Barber Creek is part of the Georgia Water Coalition.
The meeting on Thursday, October 11, will give citizens a chance to learn about the state’s Water Management Plan and Coalition efforts to make sure that water conservation, rather than simply water consumption, are taken into consideration.
Governments that promote and finance their development through the sale of water aren’t very likely to make conservation a top priority, as the current response to the drought illustrates.
Tuesday, September 18, 2007
The Bonds of Hard Labor Creek
The Athens Banner-Herald reported today that a Newton County man has intervened in Walton Superior Court to block the sale of bonds to finance the proposed Hard Labor Creek Reservoir.
Walton and Oconee counties are partners in the $350 million project, with Oconee expected to pay more than $100 million.
The story doesn’t provide much background on Samuel M. Hay III, who filed the brief objecting to the validation of the bonds, or on the grounds for the request that the Court refuse to validate the bonds.
Hay, who has a Covington postal box, has a web site on which he is described as an independent researcher who has worked with environmental issues for more than 20 years. A story in the Banner-Herald in 2002, when Hay announced he was running for Governor as an independent, described him as a "journalist, newspaper officer and print company account manager."
According to the 2002 Banner-Herald story, Hay is not an attorney, though he has "entered into and argued" legal cases as a private citizen.
The Banner-Herald story today waited until the 10th paragraph of a 14-paragraph long story to explain the basis of Hay’s objection to the Hard Labor Creek Reservoir. The top of the story dealt with Walton County official responses to the legal action.
Some of the arguments Hay makes are ones that were voiced in Oconee County before the Board of Commissioners voted on September 4 to join with Walton County on the reservoir project. Others are new.
In his "Intervenor’s Brief," which Hay sent to me in response to my request, he claims that "Walton County has failed, by all standards of the Georgia Environmental Protection Division and appropriate Federal Law, to explore and prioritize more environmentally sound, less expensive and more productive alternative sources of water for the citizens."
"The debt service on this, the largest public works project ever undertaken in this County, will raise the cost of the project to in excess of $800 MILLION DOLLARS," Hay writes.
"Families farms, homes and a way of life will be needlessly destroyed forever having been inundated by the reservoir," according to the document.
Hay further contends:
"This reservoir will evaporate up to ten million gallons of water per day resulting in a valuable loss of downstream water supply to what may be the most valuable estuary in the entire Atlantic Ocean. This coastal region which reaches from the South Carolina state line to Jacksonville, Florida is being destroyed by the lack of planning and conservation of water resources within this area. Slowing of the flows in the waterways has destroyed valuable spawning grounds for marine life whose hatch are killed upon contact with the ever increasing salt content of the marshes due to reservoirs in this region causing severe chemical changes in the brackish water chemistry."
The filing also questions whether proper legal notice about the bond validation hearing was provided in Oconee County.
Finally, it questions whether permits will be granted for the pumping of water from the Apalachee River to the Hard Labor Creek Reservoir given previously issued licenses.
The Banner-Herald was following a story in The Walton Tribune published a on September 16. The Tribune story didn’t contain much information either.
Hay’s brief is on the web site, Oconee County Observations II.
Monday, September 10, 2007
What About Those Bids?
Oconee County has tossed out the three bids it received for the upgrade of the Rocky Branch sewage treatment plant and will begin the process anew, according to Alan Theriault, administrative officer for the County.
Theriault sent me an e-mail message on September 7, three days after the Board of Commissioners (BOC) voted to upgrade the Rocky Branch plant, saying he plans "to meet with Utility Department personnel in the next several days to discuss particulars of moving forward and develop a rough time-line."
Theriault said he expected the initial step to be a "Request for Qualifications" advertisement "to identify design firms or teams that have specific experience with membrane filtration wastewater systems and that would be interested in this project."
The Utility Department had selected Jordan Jones & Goulding as its preferred bidder from among three firms that submitted bids for the project on July 31, 2007. JJ&G had proposed abandoning the membrane filtrate technology specified in the request for proposals in favor of a more traditional approach that produces lower quality water than membrane filtration.
The BOC brushed aside concerns of a full room of citizens when it voted unanimously to go forward with the Rocky Branch expansion.
On behalf of the Board of Directors of Friends of Barber Creek, I had asked the BOC to guarantee that treated water from the plant will not be released into Barber Creek during floods, to agree to treat the water to the highest level the technology will allow, and to provide for independent monitoring of the plant.
At the September 4 meeting, BOC Chairman Melvin Davis said the concerns focused on operation of the plant and should be addressed at a later time.
Commissioners Margaret Hale, Chuck Horton and Jim Luke sent me e-mail messages after the meeting restating their willingness to discuss these requests. Commissioner Don Norris said not a word at the meeting and has not written me since.
At the meeting, I asked the Board to at least pass a resolution confirming its intent to respond to these concerns, but it refused.
Citizens who have depended on the media for an understanding of what is going on with the Rocky Branch upgrade are in a bind.
The Athens Banner-Herald has yet to write a word about the September 4 decision on Rocky Branch, though it did run a lengthy report about the BOC’s decision to join with Walton County on the Hard Labor Creek reservoir. That commitment is for an estimated $48 million. The Rocky Branch upgrade is expected to cost another $8-10 million.
The Oconee Enterprise had lengthy stories on both the reservoir and the Rocky Branch upgrade it its September 6 edition. The reporting was largely on target.
The Oconee Leader didn’t report on either vote in its September 6 edition, though it did put a story on its web site that day that provided a short but accurate account of the votes at the meeting.
Neither of these papers, however, reported on what happened to the three bids or what will happen next.
On July 31, the day the bids were opened, Utility Director Chris Thomas reported to the BOC that three bids had been received and indicated that he would be back in a week with a recommendation. The Utility Department leaders also said that the BOC should decide how to allocate the new sewage capacity between residential and commercial users.
On August 7, Thomas reported to the BOC that he was recommending JJ&G for the contract. Chairman Davis tried to get the Board to move on the recommendation, but it refused. Commissioner Hale said the Board had never voted to upgrade Rocky Branch. Commissioner Horton said he was opposed to JJ&G.
Utility Department head Thomas, however, is quoted in August 16 issue of The Oconee Enterprise as saying JJ&G was "still a viable option. The Board simply needs more information."
The agenda for the September 4 meeting gave no indication of what Chairman Davis would ask the Board to do. The action item was: "Consider upgrade of Land Application System." No sewage water presently leaves the Rocky Branch site; it is sprayed on hay fields on the property in what is termed a land application system.
When I posted my report (below) on 9/2/2007, pointing out that JJ&G had proposed eliminating the membrane system, was involved in the initial planning stages for the plant, and had been selected in part by members of a firm with which it has partnered in the past, I sent it to Commissioners Hale, Horton and Luke. I also sent it to the Banner-Herald and The Oconee Leader.
In accordance with an agreement I made with Chairman Davis on August 30, in exchange for being given access to the BOC chamber projection system and for being allowed to make a 12-minute presentation on behalf of the four Friends of Barber Creek Board members, I provided Davis with a copy of my comments on September 3.
In early afternoon on September 4, Davis e-mailed me at my office and asked me to call him. He then told me he saw no problems with our request that Rocky Branch meet a higher standard of discharge, since it already was doing that. He also said the County was committed to membrane filtration for the new plant.
He did not indicate that the bids would be tossed out, that the vote would be only whether to upgrade, or that no decision would be made about the three requests the Friends of Barber Creek leadership was making.
After I made our presentation at the meeting, however, Davis asked the BOC if it was ready to make a decision to move forward on Barber Creek.
Commissioner Hale asked Assistant Utility Director John Hatcher if the County was considering eliminating the membrane filtration system. Hatcher said the proposal was to use another technology to supplement the membrane system, but membranes would still be used.
The JJ&G bid recommended eliminating membranes entirely.
Hatcher also told Hale that the upgrade will include water storage facilities large enough to hold water for 28 days without discharging into Barber Creek. He said that would be enough for any flood period. He said the upgrade would cost between $8-10 million, though earlier estimates had been $6-8 million.
Commissioner Norris next made a motion to approve the upgrade. Commissioner Horton seconded. All four of the Commissioners voters to approve. The Chairman only votes in the case of a tie.
Before the vote, I tried to get Davis to let me speak again. He ignored me. After the vote, I continued to try. Commissioner Luke told Davis he wanted to let me come forward to speak again. Davis agreed.
I told the Board I thought we had "been outmaneuvered."
During the exchange, I reminded Davis that he earlier had rejected a request from the Friends of Barber Creek leadership to speak before the BOC on the grounds that he already knew what our concerns were. He said he had not rejected our request because he had allowed us to speak that night.
Davis sent me an e-mail on the morning of September 6, saying "You received the assurance from the Board that your requests would be reviewed and decisions will be made at the appropriate time when facility operational matters are considered. I view this as a positive result. I believe we all want a facility that is effective, efficient, economical, and environmentally friendly. When all is complete, I trust we will reach that goal."
I told Administrative Officer Theriault in e-mail messages on September 5 and 7 that I want to be informed about procedures to be followed in this second bidding process for the upgrade and that the Friends of Barber Creek leadership wants to review all the steps.
I also have told Chairman Davis and Commissioners Hale, Horton and Luke that we will not go away.
Monday, September 03, 2007
Why Not Give Us What We Want?
Friends of Barber Creek has consistently asked that Oconee County officials agree to three things should they decide to expand the Rocky Branch sewage plant and begin discharging treated wastewater into Barber Creek.
We’ve asked that the water not be released when the creek is flooding, that the water be treated to the highest level the technology will allow, and that the County provide for independent monitoring.
The County plans to include holding ponds in the upgrade. It has presented charts that show the new plant can exceed the proposed standards. And helping citizens monitor the plant’s operation would be inexpensive.
So why not simply agree to the requests?
E-mail correspondence between officials and Precision Planning Inc., the County's consultant, provide explanations.
Just after noon on December 12, the day of the hearing before the Georgia Environmental Protection Division on the County’s request for a permit to discharge 1.0 million gallons per day of treated wastewater into Barber Creek, Jimmy Parker of PPI sent an e-mail message to Alan Theriault, administrative officer of the County, Melvin Davis, chairman of the Board of Commissioners, Gary Dodd, Utility department director, and Christopher Thomas, assistant director of the Utility Department.
Parker also copied the message to Wayne Haynie of Jordan Jones & Goulding and Jim Sunta of PPI. The Utility Department is recommending that JJ&G get the bid to upgrade Rocky Branch.
The purpose of the message was to explain how the officials should address "the three issues presented in the attached flier," which was the petition we circulated asking the EPD to impose our three requests on the County.
Parker said that once Barber Creek floods, the additional water discharged from the plant would produce an increase in water that is "negligible." He said: "In fact, a fallen tree would have much more impact on stream hydraulics and flood levels than the proposed discharge."
So even if the impact is minimal, why not agree to hold the water?
In times of high rain, the County will have few customers for reuse water. The spray fields at the site also will be saturated. It is at these times when the County will most need to discharge into Barber Creek.
Those of us along the creek know that it has flooded often and badly in recent years. We also know that even another tree falling into it is a problem.
So how about the higher level of treatment?
"I feel the County is already going above and beyond, and the water that will be discharged will be cleaner than the water in the Creek," Parker writes. "The real answer to this question is that it would be cost prohibitive, and the net benefits of treating to higher standards do not justify the additional costs.
"I strongly recommend that the County hold their position as ‘meeting’ the requirements established by the State," Parker continued. "If we commit to exceed those requirements, the State may possibly reduce current effluent limits, which would result in additional costs for this and all future treatment expansions."
So it is a matter of money, and not yet being required to meet the higher standards.
Ironically, PPI and JJG prepared a slide presentation for the hearing that showed the Calls Creek sewage plant–the only other sewage plant operated by the County–easily exceeds the standards set by the state on at least two criteria. The Calls Creek plant uses the same technology proposed for Rocky Branch.
So what about independent monitoring?
"The EPD has the right to do this at any time," Parker writes, "but usually these activities are limited to compliance issues due to staffing shortages."
"In my opinion, Oconee County would not object to additional downstream sampling," Parker continued. "But this is an issue that must be addressed by the State, based on availability of resources."
In other words, if the state wants to do it, it is fine with Parker.
The Board of Directors of Friends of Barber Creek has asked that the County help citizens do this monitoring by creating a fund for that purpose and posting all records from operation of the plant on the County’s web site.
These are the issues that will be addressed at the BOC meeting tomorrow night (Sept. 4).
Though BOC Chairman Davis was involved in this correspondence with Parker and the other consultants, the four other members of the Commission are unlikely to even be aware of it.
The department heads work for Davis and report to him.
The four other commissioners, however, can tell Davis and the Utility Department how to operate the plant by agreeing to the three request we are making.