Wednesday, February 08, 2017

Oconee County Commission, In Split Vote, Decided To Move Forward With Calls Creek Wastewater Treatment Plant

3 MGD Option

The Oconee County Board of Commissioners, in a 3-1 vote Tuesday night, agreed to spend $13.4 million to upgrade the Calls Creek wastewater treatment plant to 1.5 million gallons per day and prepare the plant for possible future upgrade to 3.0 million gallons per day.

Oconee County Utility Department Director Wayne Haynie argued that the county would save money in the long-run if it spent a $1.1 million “premium” on the plant now so that the county would have the option of upgrading the plant to 3 million gallons per day in the future.