Oconee County Commissioners Being Asked To Spend Money On Calls Creek Expansion Beyond 1.5 Million Gallons Per Day

At Least $900,000 Added

Oconee County Utility Department Director Wayne Haynie will ask the Board of Commissioners on Tuesday night to spend $13.5 million for an upgrade to its Calls Creek wastewater treatment plant, including at least $900,000 for expansion of the plant beyond the initial 1.5 million gallons per day of capacity.

The $900,000 is part of just less than $2 million the Utility Department asked Crowder Construction Company in March of last year to add to its estimated costs for the wastewater plant expansion.