The Hard Labor Creek Regional Reservoir Management Board has turned down a request by its general contractor for a time extension for completion of the dam in southeastern Walton County.
Construction of the reservoir originally was to be completed by Jan. 20 of this year, and the Board already had given Layne Heavy Civil Inc. an extension of 71 days. The current official expected completion date is April 1.