Sunday, November 30, 2014

Oconee County Holding Open Meetings on Mars Hill Road, Future Of Courthouse And Upcoming Legislative Session

Open Vs. Executive Session

Oconee County will hold three meetings between now and Dec. 11 that will provide an overview of the Mars Hill Road widening, a discussion of space needs for the county in coming years, and the expectations of the county’s representatives to the General Assembly as that body gets ready to meet in January

The meeting on Mars Hill Road will be from 6 to 8 p.m. tomorrow at the Oconee County Civic Center, 2661 Hog Mountain Road, west of Butler’s Crossing. Project design details will be presented to the public.

Thursday, November 27, 2014

Oconee County Commissioners Accept State Agreement For Jimmy Daniell Road But Delay Action On Daniells Bridge Road

Back Shortly

The Oconee County Board of Commissioners approved an agreement with the state Department of Transportation to go forward with widening of Jimmy Daniell Road Tuesday night but postponed action on two projects on Daniells Bridge Road.

The Board made no actual decision on what it will do to Jimmy Daniell Road, with construction of center turn and deceleration lanes one possibility and construction of four lanes, a new bridge over McNutt Creek and reconfiguration to meet with the roadway in Athens-Clarke County another.

Saturday, November 22, 2014

Oconee Commissioners To Consider Agreements For Widening Jimmy Daniell Road And Daniells Bridge Road And For Daniells Bridge Road Extension

Dec. 1 Deadline Set

The Oconee County Board of Commissioners is being asked to take up on Tuesday night project framework agreements with the state for widening of Daniells Bridge Road and of Jimmy Daniell Road and construction of an extension of Daniells Bridge Road with a flyover of SR Loop 10.

The agenda item is a response to a letter sent to BOC Chairman Melvin Davis on Oct. 28 asking for county action on a project framework agreement for the widening of Jimmy Daniell Road by Dec. 1, according to documents released Friday on the county web site.

Tuesday, November 18, 2014

Oconee County Land Use Committee Tells Commissioners To Sign Project Framework Agreements with GDOT

Action At Request Of Davis

The Oconee County Land Use And Transportation Planning Committee tonight recommended to the Board of Commissioners that it sign project framework agreements for widening of Jimmy Daniell Road and Daniells Bridge Road and construction of an extension of Daniells Bridge Road with a flyover of SR Loop 10.

Bob Sanders, Land Use Committee member, said he was fearful the state would withdraw its contributions to the three projects if the Commissioners didn’t take action on the agreements the county received from the Georgia Department of Transportation in July.

Monday, November 17, 2014

Oconee County Land Use Committee To Continue Its Discussion Of Daniells Bridge Road Flyover And Other Road Projects

Economic Development Cited

The Oconee County Citizen Advisory Committee for Land Use and Transportation Planning resumes its deliberations about county road priorities tomorrow night with the goal of giving its feedback to the Board of Commissioners in February or March.

The proposed Daniells Bridge Road extension and flyover of SR Loop 10 has dominated both of the meetings the group has held since it began its discussion of road priorities at its meeting on Sept. 9.

Sunday, November 16, 2014

Volunteers Clean Up Antioch Church Road In Southern Oconee County To Protect Rose Creek

Braved Cold

Fifty volunteers, mostly teenagers, braved the cold yesterday morning to pick up litter on Antioch Church Road as a way to protect Rose Creek, which flows through the southern part of Oconee County before reaching the Oconee River at the Greene County line.

The litter, if not collected, would end up in Rose Creek, the organizers of the event told the volunteers.

Friday, November 14, 2014

Construction Of Mars Hill Road Scheduled To Begin Next Week, Georgia Department Of Transportation Announced

Clearing To Begin Wednesday

Construction work on Mars Hill Road is scheduled to begin next week, according to a press release issued this afternoon by the Gainesville office of the Georgia Department of Transportation.

Crews are to start delivering equipment and materials to the site at the beginning of the week, and clearing along Mars Hill Road in advance of construction will start Wednesday at State Route 316, weather permitting.